IPRO 328 Midterm Progress Report

Schedule for Remainder of Project

The group will continue to work in its three sub groups to maintain focus on the various aspects of the project. The next step is to take the finalized design and make all the drawing sufficient to illustrate its intentions to the observer. The following is a timeline proposed for the completion of this as well as the inclusion what other changes can be made to Keating to reduce its heating and cooling needs as well as applications for the rest of Chicago.

10-18-04

  • Turn in midterm report
  • Finalize a plan and set of elevations for the proposed structure
  • The completion of the pumping needs and calculations for the pool
  • A review of the ret screen tests

10-25-04

  • The development of a 3D model to illustrate what the structure will look like
  • The development of the attachment manifold for the evacuated tubes
  • The selection of the equipment to be included in the mechanical room to incorporate heat gained from the structure.
  • The creation of a cost/savings document to illustrate the benefit of the structure

11-1-04

  • The development of a diagram showing all the equipment to be used to create this system
  • The calculation of energy needed to run the system
  • The further development of the 3D model of the structure
  • The creation of a document stating projected benefits of more solar thermal use in Chicago
  • The finalizing of the cost of the system document

11-8-04

  • The completion of the diagram of the system
  • The incorporation of the completed 3D model into images of the site
  • The study of further improvements to Keating for energy use reduction.
  • The creation of a document stating projected benefits of more solar thermal use in Chicago
  • The creation of a document about the incorporation of absorption air conditioning into Keating hall.

11-15-04

  • Assign work on final poster
  • Assign work on the final report
  • Assign work on the final oral presentation
  • Finalize Website info
  • Finish any incomplete tasks

11-22-04

  • Work on final poster
  • Work on the final report
  • Work on the final oral presentation
  • Finish any incomplete tasks
  • Finalize Website info

11-29-04

  • Run group practices of the oral presentation
 

 

 
Illinois Institute of Technology IPRO Home IPRO PRS IPRO 328 Yahoo! Group Contact Us